Watches the mains, starts the set when it fails, transfers the load, and puts it all back when the mains returns — with no one in the building.

Rating plate
AMF Panel
The interlock between the mains and generator breakers is the part that matters. It is both electrical and mechanical, because an electrical interlock alone can be defeated by a welded contact — and paralleling a set onto a live mains destroys it.
The cooling-down run is not optional. Cutting a turbocharged set the instant the mains returns cooks the bearings; the panel holds it running off-load first.
The assembly is ours; the switchgear inside it is genuine, authorised-channel product from the makes you specify.
Built to the same standard, and able to share a lineup with this one.

8 sets · SLC 5/05 · One bus

Auto start · Load demand

Local control · Manual
A drawing, a load list or a BOQ is enough to start. You'll get the ratings checked against the actual fault level, a general-arrangement drawing to approve, and a fixed price.